Progress of Works

Progress Update 14

posted 20 Jan 2012 13:31 by Lloyd Park

1. New skatepark - the concrete base has been laid, and construction work continues.

2. Hub building - the frame of the new building is now up.

3. Central/Island path - work continues on building the path, which will connect the hub building, to the Island.

4. New bridge - on either side of the bank, scaffolding poles have been erected, in preparation for the building of the new bridge.

5. Tennis courts - construction work continues on building the new tennis courts located next to and near the former Gardners Compound Depot.

6. New Community building - most of the external structure now built, interior fitting out work underway.

7. New bowling green - base and walls in place, works ongoing.

8. Fallen tree - a medium size tree is lying flat in the path, which runs alongside the Lloyd Park Centre. It would appear that the tree was one of several trees, lining the pathway. I presume the wind blew it down.

9. New whips - no signs of vandalism yet!
 

Progress Update 13

posted 31 Dec 2011 06:35 by Lloyd Park

1. Work has commenced on the construction of the skatepark (by Gravity Engineering Limited). A container has been positioned alongside the site and foundation work has started.

2. Work has also commenced on repainting the railings of the park, in Winns Terrace.

3. In the pathway, leading from Winns Terrance/Winns Avenue, running alongside the Lloyd Park Centre (LPC), into Aveling Fields, rain water on the surface resulted in park users having to walk around a large puddle, that left only a thin strip of dry land running alongside the LPC fence, to get around the puddle. As this is the main entry and exit point to the park, from the Winns Terrance/Winns Avenue point, the state of the path is of concern when either dry or wet. 

Progress Update 12

posted 17 Dec 2011 12:03 by Lloyd Park

1. The framework of the new hub building is now being erected.

2. The central footpath, running from next to the new hub building, to where the new island bridge will be built, has been started.

3. Fencing has been erected around the new skatepark site.

4. New lamp-posts have been erected along the footpath, running from the Aveling Park Road Gate, to the new Hub Building.

5. Low mesh fencing has been installed around the new areas of planted tress, in Aveling Fields.
 
6. The new synthetic Bowling Green and Pavilion will open in January.
 
7. FOLP are making a video of the works and this will be appearing on uTube soon.
 
 


 

Progress Update 11

posted 27 Nov 2011 23:24 by Lloyd Park   [ updated 27 Nov 2011 23:30 ]

1. Work on the construction of the new tennis courts (next to the former Lloyd Park, Gardeners Depot), is proceeding.

2. A lot of the undergrowth on the Island has been cut down.

3. Work is proceeding on the new 'hub' building.

4. Part of the outer perimeter fence, on the field adjoining the Lloyd Park Centre, has again been extended onto the area previously used by park users, with soil having been deposited within the enlarged area.

5. No work has commenced on the skatepark although we are aware the contractor, Gravity Engineering Ltd, held a meeting earlier this week to plan their attendance.

6. Work on constructing the new Bowls Pavilion is proceeding.

7. Work on constructing the new heating and power building (in the Aveling Fields, former Landscape Gardeners Depot), is proceeding.

8. Over 1300 people came to plant trees on 20th November (see Gallery for pics). Most of the trees were planted and this part of Aveling Fields will become far more ecologically friendly as the trees grow. The newly planted trees are still in place and there are no signs of disturbance.

9. Paint markings have appeared on the footpath, running from the Aveling Park entrance, to the Brettenham Road entrance. The path is a hazard to walkers, due to uneven parts of the tarmac.
 
10. Negotiations have commenced on a Lease for FOLP's HQ building, formerly the Park Keeper's office, by the Lodge.
 
11. The Walthamstow Bowls Club building will be closed this week and tests for asbestos made. It will then be demolished to make way for the new William Morris themed gardens.

Progress Update 10

posted 13 Nov 2011 00:13 by Lloyd Park   [ updated 13 Nov 2011 00:14 ]


1. Work on building the new William Morris Gallery (East) Wing is progressing, with its foundations under construction.

2. A new bus shelter has been installed in Forest Road (east-bound), on the pavement adjoining the 'front' of Lloyd Park.

3. In Winns Terrace, a section of the railings (near the junction with Forest Road), has been removed, and replaced by temporary fencing.

4. 'Mountains' of rubble remain on the Island, following the demolition of the former Waltham Forest Theatre. This will be used for aggregate in the various buildings rather than removing it from site.

5. Work has commenced on building the foundations of The Hub building.

6. Work has commenced on building tennis courts, on land adjoining the former Gardeners Depot, in Lloyd Park.
 
7. Negotiations for the Lease of our new HQ building - the old park keeper's office by the Lodge in Forest Road - have begun.

Progress Update 9

posted 1 Nov 2011 13:33 by Lloyd Park

1. The Council have attached notices on railings and fences in and around the park, to appeal for volunteers to take part in the tree planting event on 20 November.

2. The moat has been drained.

3. All buildings and structures in the former Lanscape Gardeners Depot have been demolished and construction work has begun.

4. Work has recommenced on the Walthamstow Borough Bowling Club pavillion, with erection of the external walls being undertaken.

5. The telephone box at the park main entrance gates has been repaired however the glass panels have still not been replaced.

6. Work has commenced in Aveling Fields (top soil has been scooped out), with the creation of an area for trees.
 

Progress Update 8

posted 1 Nov 2011 13:31 by Lloyd Park   [ updated 1 Nov 2011 13:31 ]

1. Community Bowls Pavilion: foundations started.

2. Biomass Boiler: trenches for piping dug.

3. Drainage works including attenuation pond and for surface water.

4. Hub area: steelworks planned.

5. Theatre: additional asbestos found, now demolished.

6. Tennis Courts: ready for surface-laying

7. Gardens: irrigation installed

8. Front Gardens - no works at present due to Gallery project.

 

Upcoming works:

1. Install Community Bowls Pavilion.

      2. Hub: access path, drainage, services, foundations.

3. Play area: start works.

4. Fields: complete pond & drainage.

5. Skate park: start works.

6. Moat repairs: start.

7. Tennis courts: surface laying.

8. Island: reduced dig.

 
 

Progress Update 7

posted 10 Oct 2011 13:29 by Lloyd Park

1. Work has commenced on digging the foundations for the new William Morris Gallery extension.
 
2. Part of the site perimeter fencing, within the park, and located in Winns Terrace, has again been pulled down.
 
3. In Aveling Park (or should that be Aveling Fields!), where the footpath, which runs from Brettenham Road, meets the site outer security fence, two security panels are now apart, with whatever was holding them together, having been removed. The outer security perimeter has therefore been breached. 

 4. Work continues on building the new Walthamstow Bowling Club Pavilion, and work has commenced on constructing the new bowling green.
 
5. A trench, containing heating pipes, and other utility services, has been dug, from the point where the path from the Brettenham Road entrance, to the site outer security perimeter meet, to a point near the existing Artists Workshop Studios.
 
6. Most of the former Waltham Forest Theatre building has know been demolished. A small section of the builiding remains, which is surrounded by scaffolding.
 

Skatepark Consultation

posted 19 Sep 2011 14:26 by Lloyd Park

 
 
 
 
Good morning all,

Thanks to those who attended on Saturday, a bullet point summary of what was discussed is included below for you all.

· The group were happy with the design and did not want to make any significant changes, the design was noted to cater for beginners through to experienced riders and was more skateboard orientated due to the demographic of the local user group.

· The one suggested change to be made to the design (subject to approval by JerramFalkus & the Council) is changing the flat bank extension to the small bowled corner so that is is brick instead of concrete.

· The other suggestions were in relation to landscaping and children running into skatepark traffic, it was proposed to do this by introducing small, steep bunds that will double as viewing platforms that could also possibly accommodate a bench &/or bins?

· Safety signage was raised in discussion and is not currently included in the package, but can be added at an extra cost. We’ll check this with JerramFalkus.

· The topic of discussion was lighting and wether or not any was being supplied for the skatepark, or if new park lighting would overflow enough to light the skatepark?

· The construction start date and completion date were mentioned several times, Gravity will discuss this with JerramFalkus and let you know once a final schedule has been agreed.

· A potential future expansion was also brought up. The current design and site parametres will allow for the skatepark to be extended North (Beyond the curved bench), South (Down from the rail and the Pillar supported Hubba) or East (Out behind the bowled corner section.) Possible items for the expansion were a bowl and further street elements such as a manual pad and more block/ledge variations.

Please feel free to add in anything I may have missed and remember that comment and feedback are welcome as usual.

Kind regards,

Jake Hipwell

Progress Update 6

posted 19 Sep 2011 13:56 by Lloyd Park   [ updated 19 Sep 2011 14:04 ]

1. A meeting has been held between the skaters and Gravity, the company building the skatepark. This has enabled all concerned to understand the designs for the skatepark and iron out any issues.
 
2. The council's 2nd update newlsetter has just been issued and is attached below.

1-10 of 24